Back Bedroom

  • Install baseboard and quarter-round
  • Install remaining wardrobe (arrival 11/2/2010)
  • Install door frame
  • Install door
  • Install door trim.
  • Install closet door frame
  • Install closet door
  • Install closet door trim
  • Install closet hardware.

Master Bedroom

  • Install trim at door
  • Install trim at window
  • Install baseboard
  • Install closet door
  • Install closet door trim
  • Install clothes rod / shelving in closet

Upstairs Hallway

  • Install flooring
  • Install baseboard
  • Install Transition piece at 3 intersections with existing floors.

Stairway

  • Paint Stair Treads
  • Paint Kickers
  • Repair Toe boards
  • Paint Stringers
  • Purchase / Install banister (Hand rail) (!!)($)

Front Entrance / Hallway

  • Repair Casing on Inside Front Door.
  • Paint Front Door
  • Clean window of Front Door
  • Purchase / Install flooring.($)
  • Install Heating Vent Cover
  • Finish Light fixture.
  • Install doorknob ($)
  • Install Door Frame to Front Room

Living Room

  • Baseboard Install ($)
  • Install Floor transition piece at kitchen ($)
  • Trim/Casing at window.
  • Trim/Casing at basement entrance.
  • Trim/Casing at hallway entrance.
  • Install Smoke Alarm (!!!)
  • Install Chandelier/Light fixture.

Back Porch

  • Structural support. It seems to be sagging.
  • Clean out construction material, salvage what is possible, mostly drywall pieces that can't get wet.
  • Scrape walls of old paint
  • Install studs/support for insulation.
  • Repair Back Door.
  • Clean out cabinet for use as food pantry/storage.

Kitchen

  • Door needs to be painted
  • Trim on door needs to be installed ($)
  • Baseboard needs to be installed ($)
  • Casing around window. ($)
  • Leaking kitchen faucet.
  • Hang new cabinets (awaiting arrival (11/2/2010)
  • Purchase / Install breakfast bar
  • Install cabinet doors (awaiting arrival 11/2/2010)
  • Install trim around pass-through window.